The City of Henderson is actively working on signal timing in the Boulder Highway corridor to improve commute times as much as possible. Check out the free Waze app to navigate construction impacts and find the best route to your destination.
Construction Updates
Median Access Closures
On May 5, 2025, five median access points on Boulder Highway closed for construction. New access at Wells Street is now open. The closures are needed due to narrowing of the median and to limit the number of unprotected turns.
Segment 1: Wagon Wheel Drive to Greenway Road
Work Hours: 6am-4pm
One lane open in each direction (two lanes when available)
Concrete curb and driveway installation, streetlight, signal, and ITS conduit installation
Segment 2: Greenway Road to Water Street
Work Hours: 6am-4pm
Two lanes open in each direction
Median prep for of BRT bus lanes, streetlight, signal, and ITS conduit install/relocation, curb placement, working on median BRT lanes
Segment 3: Water Street to Tulip Falls Drive
Work Hours: 6am-4pm
Two lanes open in each direction
Median BRT grading for future bus lanes, streetlight conduit
Median access closures at Elliott Road, Foster Avenue, Corn Street, Rolly Street, and King Street.
New access at Wells Street opens now open.
Boulder Highway. Reimagined.
The City of Henderson’s Reimagine Boulder Highway is a historic roadway project that aims to make a generational impact by reshaping the future and safety of one of Nevada’s oldest thoroughfares, Boulder Highway. This 7.5-mile construction project, designed with community input, will bring several vital roadway improvements, such as center-running transit lanes with enhanced passenger shelters, upgraded storm drain system, new traffic signals, improved lighting, elevated buffered bike lanes, landscape treatments, and more.
Reimagine Boulder Highway will not only transform one of our City’s most historic roads, it will improve the surrounding area and create positive change for residents and businesses along the corridor for years to come.